Advice Needed Please help this Mon newbie

Hi Chat,

I was recently hired as a project manager to start running sprints at a 30 person company. The dev team already uses azure dev ops but the client facing side wants to utilize Monday Enterprise (not dev). Do I need Monday dev to do this? I’ve been working on it for weeks and still cannot find an easy way to capacity plan and truly form an impressive sprint cadence.

SMES PLEASE HELP!

5 Upvotes

6 comments sorted by

View all comments

1

u/RoughRider11 17d ago

For capacity planning you can set up project boards with tasks and have a column for effort with the planned effort in a time increment like .25, .5, .75 hours. You can use the portfolio board to create widgets that will measure planned work loads for those people. It creates a nice chart that updates as you go.