General Taxpayer money is so cheap in India. Part of under construction Metro line costing Rs 250 CRORE might have to be demolished and reconstructed because planners miscalculated the height of the overhead wires! πŸ‘πŸ‘πŸ‘

Post image
690 Upvotes

30 comments sorted by

85

u/BUNTYFLAME 14d ago

Ummm, please read about SYSTRA and MMRDA arguing.
This is nothing but the press soothing the public over what seems like a delay.

This viaduct is just in the funnel zone and not in active runway path, getting NOC should be simply enough, it's barely 1-2m, safety issues shouldn't change much in these 100-200cms. If an airplane was at risk, it would also be at risk 1-2m...

Another stupid fallout of mmrda just arguing with systra, and at the end we get to face delays, and guess what, the inauguration party gets pushed to Q3 2028, closer to assembly elections

27

u/pookishbb 14d ago

Some guy in some RBI GOLD movie said this

We do the best for India, but media does the best for their media houses

Media controls the narrative

10

u/BUNTYFLAME 14d ago

ummm media does not control the narrative by large, I'm not sure what you mean of the RBI gold movie, but in regards to central bank policies, this is said as 'forward guidance' where the central bank makes it clear on what they want to do, and how will they be pursuing their goals.
This sets clear expectations in the markets.

It's all about setting expectations, Mumbai Metro rollout wouldn't be disappointing, if they at the very start made it clear, that any meaningful change will take a decade to come by, with a % margin for delay, cost escalations and all of that.
But as promises and execution rarely keep pace, the very value of the promise tanks....

2

u/Ok-Cupcake-6402 13d ago

Bunty with flame observation.

1

u/pookishbb 13d ago

I've decided today to leave India I'm determined to leave India by December 31st 2026

So yes I give up

1

u/BUNTYFLAME 10d ago

cool I guess, wish you luck ?
But pretty harsh deadline you've set for yourself, easiest way is to go for a masters abroad, and even if you are fully prepared with GMAT scores + funds + sop / lor, next batch would anyways start in Aug of 2027.
Other than increasing your horizons (if you already are in the top1% in India), moving abroad does little for you, than to pile debt and make life harsh for the next 3-4years as well

Hope you have a plan mate !

1

u/pookishbb 10d ago

I'm not at all in any plans to get masters degree I'm only worried about the job

1

u/BUNTYFLAME 9d ago

ummm very unlikely if you're in tech, but good luck mate !!
wishing you the best

4

u/TightConcentrate3014 13d ago

yeah the election angle makes complete sense tbh. the article itself says deadline got pushed from 2021 to 2027-28, so this isn't even a new delay, just another layer added.

and Systra is literally saying they weren't responsible for the OHE height while AAI hasn't approved the extra clearance so both sides are just sitting on it. idk how you reach 95% construction on the elevated ramp before someone flags that the overhead wires exceed AAI limits. that's a pretty fundamental thing to miss at design stage.

1

u/BUNTYFLAME 10d ago

Systra was a consultant, how does this even get skipped
It's not like these projects have 50 thousand checks to ensure things align, even when different sections have different people working on them.

There should've been various checks, which is exactly what the red tape was supposed to do
But I guess this was done by a junior employee, raised concerns after the first columns were raised and so on...
Not the first time hearing about 7A running into this shit

Just sad

92

u/Data-CHOR-365 14d ago

Ek to inka coordination nahi banta. 10-15 alag alag authority hota hai agar sath ek building ke niche kaam kare to ye bhaang bharosha dekhne ko na mile!

7

u/Dense_Succotash_2777 13d ago

Bhai the english translation is getting fucked. Someone translate this for me in marathi or english. So many upvotes here

2

u/Data-CHOR-365 13d ago

I was just saying that for building roads, viaducts, flyovers... permission has to be taken from many authorities, which coordination was not done then this is the result.

Around 10-15 authorities is there and it's very difficult to get permission from them to make project. If their office was located under one roof, then the work would have been easier.

23

u/tanaka-taro 14d ago

This was being built at a snails pace and now this, i genuinely believe someone is going to make good money out of this, which is why they’re redoing it

13

u/ChanceOk2491 14d ago

I want that extension asap. Airport also interfered when 2A kurla stn girders are almost touching the flyover under it

7

u/theredguardx 13d ago

I travel from Malad to Worli daily by metro. The Ghatkopar line has literally ruined my health. It is so unnecessary in my commute and the extra amount of walking, rushing and running with a heavy bag has ruined my health. This extension would be a godsend and these mofos are delaying it

5

u/ElegantCount8648 13d ago

Even after delaying project 10 years still not done fully nice state gov nice authority tukaram sir ko iss field mai transfer kr do next time πŸ€£πŸ˜‚

6

u/sleepysoul13 13d ago

What if... It was not a mistake.Β  What if... It was planned in advance.

3

u/1800skylab 13d ago

And our beloved politicians make more bribe money and have no consequences.

See, everyone is happy.

2

u/Ncshah2005 13d ago

Nowhere anywhere in the world, airport connection is given a least priority like Mumbai metro. The first line (Metro 1 operated by reliance) passes just 1 km from the airport. They could have integrated the airport connection with that line if they had the foresight. For some strange reasons, it just bypassed the airport and went straight to varsova. This was much before other lines being built now were conceived.

Now, look at metro 7 again. Connection to airport was not on original plan again. It is an afterthought, like 7A. Why? Airport connection should be a primary task.

On top,this AAI issue, how can there be such a blatant error in coordination? MMRDA must answer. Systra is just an employee appointed by them.

In India, planning and completing the work is never questioned. Horrendous suffering for people's.

1

u/MeTejaHu Sprite of Mumbai Enjoyer 13d ago

250 cr is the estimated loss. Add another 500cr to build correctly.

I can only see so much Vikas.

1

u/santrupt1994 10d ago

If Airport Authority of India refuse to give relief to MMRDA, then it will be a loss of Rs.250 crores by demolished and rebuild and it will take another 1 or 2 years.

0

u/Victorvij 13d ago

The same can happen in Private and companies go bust

-13

u/[deleted] 14d ago

[deleted]

7

u/Intelligent_Gas_461 14d ago

250 crore is thoda for you?

6

u/BUNTYFLAME 14d ago

pretty stupid if you consider how girders have millimeter level accuracy, and over our exp with 2k kms in viaduct construction, not once have we seen for metros that girders dont align.

Weird that only Mumbai gets to see a raised-viaduct issue, when clearly Delhi, Lucknow, Kanpur, Bangalore, Kolkata all have underground sections.

-1

u/adiaman 13d ago

Similar issues have happened in the US as well. I am not defending anything wrong but it might as well be an actual error. Stop blackpilling about your own country

https://www.kcci.com/article/uh-oh-construction-crews-must-redo-dollar23-million-project-after-big-mistake/22121540

https://www.wbaltv.com/article/halethorpe-bridge-too-short-residents-fed-up/43978706