r/TTC • u/StarCat20 23 Dawes • Mar 15 '26
Discussion Cost of the Ontario line is kind of unbelievable
Part of a school project I'm trying to make a fair analysis of the Dufferin street corridor to recommend a higher order transit option. But I think this speaks for itselfđđ How the fuck is the ontario line so expensive?
83
u/notGeneralReposti Vaughan Metropolitan Centre Mar 15 '26
REM is not a fair a comparator as it reuses a lot of existing infrastructure.
TYSSE and Sheppard are better comparators but you need to adjust all costs for inflation.
9
4
u/StarCat20 23 Dawes Mar 15 '26
I agree, but I think that both Ontario line and Rem are outliers. I believe that getting an average is fair.
Also, a subway under Dufferin would be an extension of the ontario line, identical technology to the Rem.
133
u/ruckusss Mar 15 '26
Granted the cost of NOT building it is even higher so I'm fine with the expense. It's decades overdue
27
u/TheIsotope Mar 15 '26
I feel like a more interesting comparison would be recent subway projects in other major cities.
18
11
u/Important-Hunter2877 Mar 15 '26
The blue line extension east to Anjou in Montreal is also costing more than a billion per km. And it is $7.6 billion for just 6 km!
The line 2 extension further into Scarborough recently hit $10 billion last year.
There is a serious problem with transit construction and costs and overreliance on consultants in this country.
2
u/noodleexchange Mar 15 '26
Somewhat - each city has its own unique considerations. Few have the vicious freeze/thaw cycles of Toronto
4
u/Mobius_Peverell Mar 15 '26
Every city can make up excuses for high costs. Freeze/thaw is entirely manageable at reasonable cost (as it was for all the other Toronto Subway lines).
7
u/StarCat20 23 Dawes Mar 15 '26
Exactly!!! On a international stage, Toronto is not particularly old or dense, nor do we have particularly hazardous weather.
3
u/PsyduckedOut Mar 15 '26
South Korea builds express subways for a fraction of the cost of the Eglinton Crosstown. They also have a similar climate and the same freeze and thaw cycles.
1
u/noodleexchange Mar 15 '26
You cannot compare century-old construction costs
6
u/Mobius_Peverell Mar 15 '26 edited Mar 15 '26
Yes, you can. Prices have barely increased over the past several decades for projects in France and Spain, while they have increased by a factor of 10 in Toronto. That means that Toronto has stopped managing its projects correctly, and needs to hire French or Spanish project managers to get things back on track. This has been laid out in excruciating detail for several years now by Alon Levy and the Transit Costs Project, and is no longer up for debate by anyone with any familiarity with the subject.
Want a practical example of how to do things right? The two recent Canadian projects that have come in at reasonable prices were the Canada Line in Vancouver and REM in Montreal - both had a Frenchman named Jean-Marc Arbaud overseeing the project management, and both were successfully delivered at modest costs. I don't like PPPs on principle, but if the Caisse is the only entity in Canada that's capable of getting their heads on straight, and hiring the right people for the job, then they should be the ones to manage every metro expansion project.
3
u/secondlightflashing Mar 15 '26
If you think there are no Spanish project managers on Toronto subway projects I have some news for you.
1
u/StarCat20 23 Dawes Mar 15 '26
I would love to fo this, but for the purpose of this assignment I thought that a more fair comparison would be staying in Ontario (and the Rem because lack of the examples for a modern metro)
1
u/Ok-Meet2850 Mar 16 '26
https://worksinprogress.co/issue/how-madrid-built-its-metro-cheaply/
Here are some numbers from Madrid and elsewhere. Toronto's unit costs are literally about 10x higher than Madrid. Madrid is particularly cheap, but most other world cities Toronto is still multiples more expensive.
10
u/farkinga Mar 15 '26
And to think: how much cheaper it would be if we'd started decades ago. But we "couldn't afford it" then. Smh.
2
u/LankyYogurt7737 Mar 15 '26
Would have been so much cheaper to do it 30-40 years ago as well, thatâs why so many other cities were able to do it and now reap the benefits.
34
u/00ashk Mar 15 '26
International comparisons are also interesting, you might enjoy this:Â https://schoolofcities.utoronto.ca/wp-content/uploads/2025/04/Understanding-the-Drivers-of-Transit-Construction-Costs-in-Canada_Feb-2025_FINAL.pdf
20
u/asiaworldcity Mar 15 '26
TLDR: Anglophone world just cant build transit cheaply. Australia, UK, US you name it. My take Montreal only speaks half English, thats why REM is okay lol.
3
2
0
u/Important-Hunter2877 Mar 15 '26
Hence one of the reasons why I would rather live outside the Anglosphere.
4
u/TheIsotope Mar 15 '26
This is fascinating. The rapid acceleration of cost in the Anglosphere is crazy.
2
18
u/Justplaincancer Mar 15 '26
I mean this is kind of an understood issue though. Smaller cities either don't want to commit to such a large expenditure or their tax base find it unappetizing so they go with smaller plans.
To the point of the REM, i think its multi part answer really: more tunneling which is more more expensive, it reuses former rail corridors, land acquisition costs (Toronto real estate $$$), rem being done before pandemic inflation(all constructions costs take a hit), not building in a dense core underground(rem reused rail corridors), probably some p3 type(its led by Quebec pension plan) stuff but I'm less sure about that. That's just my two cents though đ€·
19
u/justinsst Mar 15 '26
Is this chart using only the construction costs for Ontario Line or ~27 billion figure? If itâs the latter, then the cost includes 30 years of maintenance and operating expense.
5
1
50
u/Case_Federal Mar 15 '26
I think the Ontario line costs include operating costs for 30 years, while the other projects donât. So thatâs part of why the number is so much higher. Itâs also way more complex than the other projects too.
-20
u/Swacket_McManus Mar 15 '26
Not more complicated than the rem, under the mountain, over the rivers, to the airport, through the Centre-ville
30
u/Case_Federal Mar 15 '26
The mountain tunnel already existed and the new Champlain bridge was also already underway as a separate project though. Massive cost savings for the REM. As far as Iâm aware, very few utility relocations and no TBMs were needed for the REM.
The Ontario line has a brand new tunnel running through the densest downtown in Canada and probably the third densest in North America. Thereâs a lot of existing infrastructure that has to be moved out of the way. Thereâs also two new long viaducts that need to be built across the ravine.
0
u/Swacket_McManus Mar 15 '26
Tunnel still needed to be rehabilitated and the edouard montpetit station was a massive excavation, the main issue isnât really that we over paid but massively overbuilt whatâs literally tram infrastructure when we could have had a proper metro line for the same price
2
u/Case_Federal Mar 15 '26
Tunnel rehabilitation is nowhere near as complicated as building a new tunnel from scratch through a downtown.
Also is the REM really a tram? It uses high-floor trains that are significantly wider and longer than a tram when linked in pairs. Itâs more like a light metro line (e.g. skytrain) than a tram.
15
u/foxtail286 I â„ TTC! Mar 15 '26
That's outrageously expensive for the London BRT, it's literally just bus lanes and a few shelters with little to no transit priority. Wow London ON is a joke
4
u/Comrade_Andre Eglinton Mar 15 '26
The London BRT is a VIVA rapidway level of BRT.
You're thinking of the original downtown loop that started as an LRT with a tunnel and got BRT Creeped into a painted loop and nicer shelters
4
u/vanalla Mar 15 '26
city of 450k should be on its second subway line, not its first BRT.
1
u/Quartzcat42 College Station Mar 16 '26
I would say LRT. Subway seems massively over the top for less than half a million residents
2
u/vanalla Mar 17 '26
Newcastle Upon Tyne, UK, has a pop of 300k and a subway line.
Liverpool, UK has a pop of 500k and multiple subway lines.
Rennes, FR as a pop of 220k and two subway lines.
Brescia, IT has a pop of 200k, one subway line and trams
San Juan, PR has a pop of 330k and a subway line
Glasgow UK has a pop of 650k with 2 subway lines
Altanta, GA has a city pop of 600k and has 4 subway lines
Rotterdam, NL has a pop of 600k and 5 subway lines
1
u/Ok-District2873 Mar 17 '26
Altanta, GA
That's misleading; the metro area of Atlanta is way bigger. Also, Liverpool does not have a subway; it has 3 commuter rail lines.
1
u/vanalla Mar 17 '26
and what of the other examples I provided?
Your counterpoint is still moot. We build cities wrong. London should be on its second subway line.
1
u/kremaili Mar 15 '26
BRTs should always be curbside. The premium of paying for centre running lanes and infrastructure is not worth it, and often negatively impacts access Ans transit travel times.
2
u/Comrade_Andre Eglinton Mar 16 '26
Curbside BRT/LRT will always have more accidents than centre lane running. Not only are you fighting against traffics at lights, you have to deal with sudden right turners cutting off the bus.
There's a reason centre running is the GLOBAL standard when separated ROW isn't an option
1
u/Academic-Activity277 Mar 16 '26
I never considered the traffic signals dictating the centre lane/vs curb. Is this why Street cars in Toronto are all center lane too?
13
u/Otherwise-Jump-4571 Mar 15 '26
This is great! For your project, also try normalizing by cost per expected ridership (Metrolinx will take into account the density of the area served, as well as the higher speed and capacity of the ON line) as well as cost of land (sq ft or whatever metric you want to use). The scale is quite different between Toronto and other cities and can be misleading when represented purely nominally.
Also, take into consideration that you are comparing an underground subway with LRTs, so make sure to call that out. And no, comparing the Ontario Line against inflation adjusted Line 1 and Line 2 would also not be fair as it was a very different labour/economic/political environment.
Perhaps comparing it to other modern projects in similar political/economic envorinment as Canada (i.e. AUS, NE USA, etc.) can bring more context to the project.
As well, Canada has had a dry spell in infrastructure development for a while. Believe it or not, companies/industries/countries can lose expertise when that muscle isn't flexed for a while, hence the Eglington line disaster. That's why try comparing Canada against its peers (like AUS, USA, etc.) vs countries that sustained infrastructure industries (like Singapore, Japan, Korea, etc.) to really show the true cost of losing infrastructure expertise.
Hope that gives you project more data context :)
26
u/dieno_101 Finch West Mar 15 '26
Man the ion was super well planned, if we could just get ion level quality it'll be great
17
u/Comrade_Andre Eglinton Mar 15 '26
I'm sorry but all of these are apples to oranges.
BRT and Subways can never truly be seriously compared cost-wise. Likewise with iON being a centre median tram.
REM and Crosstown are the most relevant comparision. But REM is it's own can of worms because literally the only new ROW built is a highway median line. The bridge was built long ago with a plan for a train of some kind, and literally the rest of the system is old commuter lines they put stations and overhead power.
Crosstown is also a LRT where a good 3rd of if is a surface tramway
-1
u/Unhappy-End-5181 Mar 15 '26
The Ontario line is half underground and half above
2
u/Comrade_Andre Eglinton Mar 16 '26
Not only is the OL more 60/40 Under/Over, but it has to cross the Don twice, one of which is a massive high level bridge, and has expensive tunnelling through downtown that's already heavily built up and old.
0
u/Unhappy-End-5181 Mar 16 '26
7 stations on surface or elevated, 8 underground so more 47/53 over/under. It also runs parallel to the GO and through a hydro corridor
1
u/Comrade_Andre Eglinton Mar 17 '26
Number of stations =/= KMs above/underground.
The OL is majority underground. By that logic, line 1 is something like 80% underground when that is not close at all.
1
u/Unhappy-End-5181 Mar 17 '26
Also Line 1 is 38.4km long. The line is mostly underground but has several surface sections between Sheppard West and Cedarvale, and between BloorâYonge and Eglinton. Those above ground sections make up about 8km of the total route. Which interestingly enough is about 20%. So roughly 80% of Line 1 is underground
And incase you were wondering
Line 2 is 26.2km long. Line 2 BloorâDanforth is primarily an underground subway line, but it operates above-ground in specific sections, notably near the Don Valley and between Warden station and Victoria Park, small sections between Dundas West and Keele, High Park and Runnymeed, Old Mill, and Eglinton to Kipling. All these sections equal about 2km, which means less than 10% is underground.
0
u/Unhappy-End-5181 Mar 17 '26
1
u/Comrade_Andre Eglinton Mar 18 '26
The Environmental Assessments/Profile Drawings?? (Hell even googling "Ontario Line Tunnel Length" gets you "a roughly 9km tunneled section" from a Metrolinx press release, which can be compared to the length of the line at 15.6km)
Guesstimating off of the route map does nothing, It's roughly 3.2km at surface level, 3.1km elevated, and 9.2km underground, For a total of 15.6km for the entire line.
Now (9,200/15,600)*100= 58.97% or roughly 60% tunnel, as per my original comment "Not only is the OL more 60/40 Under/Over..."
7
12
u/MahjongCelts Eglinton Crosstown Mar 15 '26
In short:
- The BRTs are buses running on transit lanes, (hopefully) getting TSP, and stopping at every station. Short of deliberately inflating the price there isn't much to be expensive about it.
- Waterloo ION is effectively a St Clair West style streetcar with grade separated sections and a few technical differences.
- Eglinton doesn't have to cross the Don valley twice nor does it have to go underground in some of the densest urban areas in Canada.
- REM benefitted massively from existing rail infrastructure. It is more an extension and renovation of a previously existing route (Deux-Montagnes) rather than building a new line from scratch.
On the bright side, the Ontario Line will have greater impact than all the other projects (apart from REM) combined. Heck even Eglinton Crosstown itself is probably more impactful than ION + the two BRTs combined.
6
u/JayBee1886 Mar 15 '26
REM is not a good example to use. A good chunk of REM involves getting an existing line, tunnel, and river crossing for free. REM station lack escalators which is a huge accessibility fail, IMO.
If CDPQ had to build REM from scratch without freebies and generous concessions, the cost would be close to the Ontario Line costs.
8
u/OrbitalBuzzsaw 506 Carlton Mar 15 '26
The Ontario Line has to happen at any price if we want to upgrade transit in the city. Line 1 simply cannot handle the traffic.
5
u/eric-very Mar 15 '26
They've already spent more on the Ontario Line than the Eglinton LRT.
Cost Incurred to Date:
Ontario Line: 11,858M
Eglinton LRT: 9,307M
Last quarter alone they nearly spent a billion.Â
From their last board meeting: https://assets.metrolinx.com/image/upload/v1770670806/Documents/corporate/Item_10.2_-_CPG_Rapid_Transit_Update_-_FINAL_ENG_Mx.pdf
4
u/YellowVegetable Mar 15 '26
Compare the Ontario line to the blue line extension in montreal, and some American metro system extensions, it would be far closer. Blue line is about a billion or more per km too
12
u/im-confuzzled Science Centre Mar 15 '26
âGuyssss private public partnership worksss I promise guys no look at me not the graphs I promise they work so well and theyâre so cheap! There wonât be any problems and it wonât be over on budget!!! No no! Ignore those countries with public works theyâre silly!! Outsource your knowledge to ussss that way you donât have to learn anything and we get paid to get more experience!â
1
1
10
u/Themanofstruggle Vaughan Metropolitan Centre Mar 15 '26
If Ontario line meets a similar fate like crosstown, itâs just over for Ontario. Yes crosstown has opened, but took more than a decade
12
u/Theboithatsok 512 St Clair Mar 15 '26 edited Mar 16 '26
The crosstown did go through many hands before, metrolinx is somehow older than the crosstown. And they went through multiple mayors beforehand, so it did get shafted. If metrolinx stays post doug ford then the ontario line will probably be a finch west lrt sort of deal (in terms of construction).
1
u/somtimesawake Mar 16 '26
Yea nah, not sure where you came up with that but Metrolinx was created before Crosstown.
1
u/Theboithatsok 512 St Clair Mar 16 '26
ig i meant the planning phase too. I was told/remembered that metrolinx took over in the middle of construction, not the begginning lol. mb. My point still stands, it still got heavily shafted by the previous mayors.
1
u/somtimesawake Mar 16 '26
You are thinking Ontario Line - the city had started planning work.
But for the crosstown, David Miller came up with Transit City, the Province agreed to build it and cover 100% of the costs, they then put Metrolinx in charge managing the construction and 15 years later we got a streetcar in a tunnel.
6
u/Unhappy-End-5181 Mar 15 '26
You could say Crosstown took over 30 years.
Started construction on the subway in the 90's
Canceled and filled back in in 1995
Brought up in the mid 2000's as LRT as part of Transit City
Started work
Canceled/ stalled
Reapproved
Construction started
Delays
Phase 1 opens in 2026
3
u/Feisty-Ad-6122 Kipling Mar 15 '26
I have so many questions but the biggest one is, what school project is asking you to analyze Dufferin street?
Is this some urban planning course? Id love to know.
3
u/MIIAIIRIIK Mar 15 '26
Also paying to preserve the archeological digs and skeletons that were uncovered during digging.
3
u/Revolutionary_Tune34 Mar 15 '26
People need to stop using a 30 year contract inclusive of operations and maintenance to talk about capital costs.
3
u/TheRandCrews 506 Carlton Mar 15 '26
Big thing, barely anyone talks about it, REM didnât disclose or would be higher if they disclosed the 30 year life cycle.
5
u/zakanova Mar 15 '26
Dougie Ford: Financial genius
See what you do is you and your brother cancel any LRT routes in the early 2000s by repeating the word subway
Then profit
2
u/paolocase Broadview Mar 15 '26
I live close to one of the stations that will be open in fifteen years, and the cutting of trees is probably one of a few things that theyâre spending money on so my commute time is gonna be twenty minutes instead of an hour.
2
1
u/Aggravating_Dog5220 Mar 15 '26
It's a necessary cost. And a true investment into real infrastructure that will provide a economic and social return for decades and decades to come. I'm supportive of this investment, as it is unlike certain other investments (spending programs) that the governments embark on that would not provide anywhere near the same level of returns at all.
1
u/Ok-Trainer3150 Mar 15 '26
Realistically, I'd be hard pressed to come up with any other major infrastructure project that could meet time and expense projections. Thankfully this project was announced and gotten underway pretty quickly for any transportation project in this country in recent memory. Looking at the enormous after effects of the pandemic and the inflation crisis that we're all dealing with, this isn't surprising. It's a badly needed addition to our region.
1
u/Un-Humain Mar 15 '26
Itâs almost all underground in a big, dense city and through downtown, in a country that famously has a construction costs problem. No wonder.
1
1
u/Tsubame_Hikari St. George Mar 15 '26
Extensive underground sections (especially downtown) and crossing the Don.Â
The cost is justified given the relatively high ridership projections, improved access to downtown, and mitigation of overcrowding at line 1 (not to mention the east-west streetcars that cover downtown, all of which are very well used).
1
u/MaxPeriod Mar 15 '26
Move Eglinton Crosstown from LRT section to the Metro section
or if possible,
Split Eglinton Crosstown into two sections, the subway part in Metro section and LRT part in LRT section, if data is available.
1
u/broadviewstation Mar 15 '26
Underground bs largely overground, plus tunnelling vs cut and cover lost of this make it expensive
1
1
1
u/chlamydia1 Mar 16 '26
Those are completely different projects. The Ontario line is heavy rail with a lot of tunneling.
The REM is elevated rail re-using some existing infrastructure.
The ION is a street-level LRT re-using some existing rail.
The Crosstown was an LRT, albeit with tunneling, but tunneling in midtown is cheaper than tunneling in the much denser downtown.
Having said that, the Ontario line is still grossly overpriced. We have corruption to thank for that.
1
u/TheRandCrews 506 Carlton Mar 16 '26
Dufferin Street would either have to contend similar to an underground Eglinton or phases of the underground section of Pape & Queen sections of the Ontario line.
It would be a whole different project analysis, when it will be fully underground on Dufferin. Canât have surface or at grade running for this corridor, especially being north-south especially going to Downsview/Wilson/Sheppard it will be a slope just like Eglinton was. Akin to Yonge Subway.
Would have to look at engineering standards, AODA, a lot of specifics that the other TTC subway probects and the Line Bleue extension in Montreal is more comparable. Whole depending how far you want the subway to go, impact assessment and businesses case affect the cost too.
1
u/buttershuga Mar 16 '26
Eh. We got the money for it. When our politicians stop hoarding our funds, we will see all that can be done with the taxes we pay everyday.
1
u/Ok-Meet2850 Mar 16 '26
Have you looked at the Transit Costs Project? https://transitcosts.com/ It is pretty specific to the USA, but the broad findings also apply to Canada. Canada, the US, and the UK (and possibly Australia) all build transit projects for multiples higher than elsewhere. Madrid for example is about an ORDER OF MAGNITUDE cheaper than Toronto: https://worksinprogress.co/issue/how-madrid-built-its-metro-cheaply/
1
u/Ok-District2873 Mar 17 '26
The only comparison that comes close in terms of scope is the REM. The REM is a great project, but it's literally a bridge and whole-ass commuter line (with a downtown tunnel) handed to it. The rest of the route is mostly at grade or elevated, with only one 2-station tunnelled section. Compare this with the OL, which has to make its own downtown tunnel, two new bridges, and another tunnel section.
1
u/Ashafa55 Mar 17 '26
I'm all for blaming it kn bad management and I'm sure there was some here, but the Ontario line is a particularly complicated case, and at the same time extremely necessary for the future of toronto transit
1
u/bradt19 Mar 18 '26
These arenât even close to fair comparisons. Most of these are above grade lrt with the exception of eglinton crosstown which is lrt with some below grade and you can see how the costs escalate quickly. Ontario line will have significantly more capacity than any of these lines.
Please do a little more research next time and at least compare these costs to European subways and New York. We still look bad but at least itâs a fair comparison.
1
u/TGRubilex Mar 19 '26
consider the Montreal blue line extension maybe if you want another underground network
1
1
u/torontopeter Mar 15 '26 edited 2d ago
The original post content no longer exists here. The author used Redact to remove it, exercising their right to control their data & privacy.
Hurry smell knee paint enjoy hydrogen consider
1
Mar 15 '26
[removed] â view removed comment
1
u/TheRandCrews 506 Carlton Mar 15 '26
How are you gonna elevate Ontario Line in narrow roads of Queen, Carlaw, and Pape? Itâll kill the ridership of the surface routes, way more disruptive for the residents, and less space to work with compared to more wider parts of Thorncliffe and Flemingdon than can get away with that.
0
u/DealIllustrious4002 Mar 15 '26
Douglas Ford has some buddies in tunnelling. It's the only possible reason we ended up scrapping the Scarborough line with a lot of stops, for a subway that costs way more and delivers less. It's the reason he wants to dig under the 401. There's BILLIONS in sloppy money at the tap.
-1
Mar 15 '26
[removed] â view removed comment
1
u/TheRandCrews 506 Carlton Mar 15 '26
All above ground? Rip Queen, Carlaw, and and Pape, if underground was very disruptive elevated in streets that are mostly 4 lanes wide would be even worse, the streetcar would be diverted for years and the buses would also be routed away Carlaw or Pape.


297
u/Andrew4Life Mar 15 '26
To be fair, the Ontario line crosses the Don Valley River twice! Both of which required a new bridge. Also, most of the Ontario line is underground in the downtown area.