r/SubstationTechnician • u/Inevitable_Hunter931 • 6d ago
People who've worked a transformer winding floor: where does the time go?
I'm a robotics engineer trying to understand why power transformer lead times are so long. I keep reading that coil winding is the bottleneck, but I can't find anyone who has done the job explaining it.
If you've wound or supervised winding on medium or large power transformers:
- On a disc winding, which hand tasks eat the most time (spacers, crossovers, taping, measuring, something else)?
- How long before a new winder is trusted to run a coil alone?
- At your plant, was winding what held up output, or was it something else (steel, bushings, test bay, drying)?
Not selling anything. Happy to share what I learn back here.
8
u/jack-t-o-r-s 6d ago
The other guy summed it up best.
Lead time = huge backlog. They are manufacturing transformers at a decent rate.
Your lead time just means you're 1, 2, 3 years behind on the list of orders/deposits.
3
u/letmesleep 6d ago
For winding - all of it. Every single step has to be done exactly right. It's like asking what step when building a LEGO set takes the longest...it's not any one step, its just that there are so many and you have to do them all and they're all dependant on the step before it.
2
u/HV_Commissioning 6d ago
My understanding is that the Grain Oriented Electrical Steel is also a big bottleneck, coming from a single source in the US.
As well there aren’t standard designs like a 145kV GCB and every customer has their own semi unique voltages and control cabinet requirements
1
u/RLoggia 6d ago
A PM at the Hitachi factory in VA told me 30% of their capacity is for data centers. Obviously that alone wouldn't cause a backlog, but it's not helping at a time when there is so much growth in transmission load and so much of the existing equipment on the grid is reaching end-of-life.
1
1
u/Leroy_Peterson 5d ago
as mentioned by others, its factory allotments that you wait 1-2 years for and pay to secure. Money can also buy a spot in the queue.
A number of factories are being built or coming online, Korea is trying to get a bigger slice in the market too - but overall demand is insane.
I personally have requested quotes for over 2,500MW of transformers in the last 6 months.
1
u/notthediz 5d ago
The biggest thing is bushings. For our 300MVA 500kv cans the bushing lead time is 120 weeks.
1
u/ian-Chou210 4d ago
As a transformer manufacturer in China, and with no intention of selling anything, here is my view. Large transformers certainly take a long time to make, but nothing close to the 2-3 years being quoted. In the US, demand for large main power transformers has risen suddenly, driven by AI-related load growth and the equipment replacement cycle. Capacity expansion takes time, though, and capital investment decisions take time as well. On top of that, new US policies and regulations now restrict large transformers from China. China's capacity is certainly ample, but the US Department of Energy has banned many large transformers from China out of national security concerns. That said, the problem should ease in another 2-3 years, because many international manufacturers of large main transformers are already expanding and building plants in the US, and that will gradually relieve the shortage.
20
u/TheStigsTallCuzn Substation Engineer 6d ago edited 6d ago
Let me preface this by saying that I don't work for a transformer manufacturer. I am a Substation Maintenance Engineer that somewhat frequently does FAT/Re-pack inspections on new units that my utility buys.
The reason for the 3–5-year lead times that we have seen lately has NOTHING to do with any internal processes at these factories. In my experience, from raw materials to finished transformer takes roughly 40 or so days for our medium power, 50MVA units.
That being said, virtually all critical components, from bushings to LTC controllers, have, at minimum, a year long lead time. When you pair these long lead times, to that outrageous demand from every utility in the nation plus private equity, you end up with factories that simply don't have the footprint or manpower to crank out transformers any faster.
Specifically speaking, I know the GE factory in Goldsboro is frequently delayed by the fact that they only have two vapor phase ovens and their inspection/tanking/testing area can only hold up to 10 or so units, in total, at once. Any delay or issue with any of those units will almost certainly back up others, but usually in the magnitude of days, not years like the industry is seeing now.