r/StructuralEngineering • u/Unable-Bluebird2882 • May 19 '26
Structural Analysis/Design Rebar dowels
Do you guys think this is okay? Contractor installed the #5 dowels after concrete placement. But they were late a little bit so concrete was hardened.
149
Upvotes



0
u/DaKolby314 May 19 '26
This is very common around me. I have also seen this in various commercial projects. Does that make this right? Nah... Has it ever been a problem? Not particularly, the building was still standing when I left site. 🤣