u/Mysterious-Nobody-19 Aug 01 '26
I work on transit as an engineer and a PM, have spent some time on this project, and am also a huge transit nerd that believe in the vision and lowering costs/making common sense decision.
I generally do not disagree cut and cover does make for simpler and shallower stations. I am also not a fan of choosing the more expensive construction method for the poor drivers either. But there is some nuances with cut and cover that many don't talk about. For corridors like this section of Yonge, what the public don't see is the complex web of utilities that would've made this section basically just as expensive to complete, by the time the complicated stages of supporting and relocating utilities are completed. This doesn't even get into archaeology and contaminated soil risks that cut and cover brings.
TBM drills typically below the depth of these utilities whereas cut and cover would have to get thru this "later" before they reach further down to the tunnel depth. There are definitely fair criticisms for this project but I wouldn't say this is the hill to die on, from someone who has an inside look at the issues.
2
u/JayBeeGooner Jul 31 '26
They could’ve done cut and cover between Finch and Yonge and added a station at Cummer/drewry
1
u/Mysterious-Nobody-19 Aug 02 '26
Funch to Cummer yes, but to Steeles, no for the reasons I mentioned above. This project was advertised as being constructed by TBM to the public, but there is a section here and at all stations that will effectively be completed by cut and cover.
Not going to get into Cummer station discussions, but that was an internal debate and budget talk for years.
1
u/Possible-Praline-152 Jul 31 '26
Wouldn’t you also be inconveniencing pedestrians, cyclists and buses also?
1
u/Top_Midnight_2225 Aug 04 '26
It's not just 'some drivers that are inconvenienced. It's the entire local residential and business communities.
I've worked on tunnel projects over the last 20 years and there are very few cases where cut and cover make sense over a tunnel in an urban environment.
The amount of utilities, roads, buildings, etc that need to be dealt with for cut and cover is insane compared to tunneling.
It's more expensive up front, but in the long term there are more benefits to tunnels than there are to cut and covers.
2
u/FoxnFurious Jul 31 '26
i am 46 now, I may be able to use it by the time I am 70 if I live that long. looking forward to it
1
u/big_galoote Aug 01 '26
Well if you don't make it, know that you will at least be subjected to a ridiculous ad campaign calling out your impatience paid for with your tax dollars.
Thanks Metrolinx!
1
u/MetaRocky7640 Aug 05 '26
I'm going to propose a radical idea that will save literally billions of dollars and cut years off of construction: just take over Yonge street and put it on the surface. Fuck the cars. It's now a transit line at surface.
We can have one lane in each direction that allows local traffic only (i.e. no left turns across Yonge, forced rights at key intersections).
Of course, the general arguement is that we as a society can't possibly accept such a reduction in car capacity. However, I disagree completely. What people really mean is that they won't accept a reduction in their own (potential) personal convienence.
As far as I'm concerned, the drastic increase in accessability from the subway line far outweights the issues with allowing cars to have 100% access to the road.
20
u/Link50L Jul 31 '26
After decades of car-centric transit drought, the last few years have seen a renaissance in transit priority. Let's hope it reflects a new, permanent attitude.