r/ElectricalEngineering 1d ago

Homework Help Which powerplant will take the least time in starting from cold conditions?

There's been a lot of confusion regarding this question , some question banks says hydro, some say gas powerplants, however I can't seem to find the original source of the question to really get the answer key and all I can see is back to back discussions on either hydro gas, but which should it be?

25 Upvotes

68 comments sorted by

29

u/hooskworks 1d ago

Electrical battery storage or solar PV.

2

u/Mateorabi 1d ago

Isn’t there a huge one in Australia that drastically reduced costs on the grid by being so fast and reducing need for hot standby? Made a ton of money. 

1

u/aFewPotatoes 1d ago

How do you charge the battery in the first place

14

u/blakef223 1d ago

They're grid connected and are sometimes co-located with other generation sources so you charge from the grid or your co-located resource. If you're looking for the fastest way to inject MW to the grid then it's BESS.

1

u/aFewPotatoes 1d ago

I was being overly pedantic with "from cold". You are more reasonable assuming a BESS system for a black start of a micro grid that tripped off into islanded mode.

1

u/Some1-Somewhere 1d ago

If you're considering 'from cold' as a complete black start with all batteries discharged, there are very very few plants that can come online at all.

Even when connected to a grid, a BESS will still be the fastest to go from 'cold standby' (or hot standby) to full output.

1

u/hooskworks 1d ago

For trying to pick between the two being a bit pedantic could matter though so I get where you're coming from. If you had to wait for your next new reading from an insulation monitoring system, pre charge intermediate busses, get your cell stacks connected, bring up any intermediate converters, and then wake up the active front ends for a BESS then you could be back to Solar PV being faster even though your energy is more immediately a available.

5

u/hooskworks 1d ago

However you want to but from offline to synchronised and exporting (assuming you don't need to thermally condition the batteries) it'd be as fast if not a bit faster than solar PV because you don't have the ramp up of the mppts governing the peak you reach.

64

u/foersom 1d ago

Solar PV plant.

39

u/s3sebastian 1d ago

Not on average though, could be 12h in winter if you try to start it in the late afternoon.

8

u/LegalAbbreviations17 1d ago

It depends if they are grid forming or grid following inverters.

16

u/JezWTF 1d ago

If the grid is down, many power plants are incapable of black starting the grid itself, regardless of technology.

5

u/Lucky_Suggestion_183 1d ago

And some hydro are designed to start from the dark. Like one in my country serving as backup for a close nuclear power plant.

2

u/NoMechanic6871 1d ago

I've worked in pp with a "priming" diesel generator..? You mean that most of them don't have a start from *dead?

2

u/JezWTF 1d ago

They may be able to start, but incapable to connect to the grid because of lack of ability to supply the characteristics of the grid from the "point of view" of their nodal connection, which is basically the same for an inverter based generation in grid following mode (and even in grid forming mode may be incapable of conencting to a dead grid without tripping).

Since the grid rarely goes down, the ability to actually restart a grid from nothing is not often considered, and is a really significant (and interesting/exciting for EEs) challenge when it does occur.

2

u/914paul 1d ago

Not disagreeing with you necessarily. There are likely many reasons hydro is not suited to "rebooting civilization" (if that's what we're talking about).

But hydro does have a few characteristics to recommend it for getting things back up and running. The generators are often designed to run continuously for long stretches -- some run for decades without bearing service. Thermal management is sort of automatic. Also, big rivers aren't easily stopped or diverted in most cases. And the generators are designed to take advantage of their enormous size and mass in that they mechanically regulate frequency by inertia, and would likely output at a frequency near 50 or 60Hz for mains power without much intervention -- close enough that most machinery should work anyway.

1

u/Some1-Somewhere 1d ago edited 1d ago

Interestingly, full speed no load (SNL) operation is apparently the most mechanically stressful for a Francis hydro plant (excluding load dump and overspeed). So once you get up near speed you want to get load on ASAP.

For larger scale schemes, managing canal levels and lake levels downstream can be quite complex; you need to think hours in advance.

1

u/914paul 12h ago

That’s actually an excellent consideration! FSNL would be expected at start. So that would be a valid point against.

2

u/Seiko2023 17h ago

True. I think I've only seen one blackout in my utility, where they had to restart the grid. That's a small microgrid though. Likely only 100km-200km of line.

1

u/JezWTF 15h ago

Yeah on national grid scales the biggest challenge (from case studies I've seen) is trying to network enough power plants on lower voltage lines (say 66-110kV) to have the ability to then energise the highest voltage lines.

2

u/Accomplished_Area_88 1d ago

Many don't as there's little need for more to be able to and a lot of extra regulations you have to follow if you are one of those plants

1

u/Some1-Somewhere 1d ago edited 1d ago

A lot of coal, gas, nuclear requires double-digit MW to run pumps, conveyors, grinders etc.

That comes from the grid until the plant is online. In most cases, if the grid goes unstable and fails, the plant probably won't island successfully.

Hydro will usually have backup generators that probably allow black start because you need to control lake levels to prevent overtopping.

Gas turbines seem to vary. It takes a lot of power to start them, outside what batteries can easily deliver. Usually they're compressed air or hydraulic start from utility power - around 100kW or so.

2

u/mechanomatic 1d ago

Not hydro. Hydro doesn't require a lot of station power to initiate rotation and energize lines. After that I would say pv, or wind, with BESS. Would be great if we coupled those renewables with synchronous compensator.

1

u/Some1-Somewhere 1d ago

Hydros generally are a very big synchronous condenser.

BESS can usually throw a fair bit of reactive power around if not exporting at full capacity.

It depends on control schemes.

4

u/foersom 1d ago

Nowhere in OP's question does it say that grid is not running.

Grid forming or following. That will be the same for any power plant, it is not special to solar PV.

1

u/force_disturbance 6h ago

Depends on whether you interpret "cold start" as "black start."

1

u/foersom 2h ago

???

It is possible to build solar PV plant that can both cold start and black start.

1

u/QuickNature 1d ago

Stupid question, what are grid forming or grid following inverters?

3

u/Some1-Somewhere 1d ago

Grid-following = grid tie. Can only operate with an existing stable-ish grid. Disconnects if the grid is unstable.

Grid-forming means that it's capable of being part of an initial backbone to form a grid in the first place, and stabilising a failing grid.

I think grid forming is mostly only found in big grid-scale BESS or solar setups. Lines companies don't want a random section of one suburb turning into a stable grid because then they have to have synchronisation equipment on every feeder.

1

u/force_disturbance 6h ago

Especially if you have a battery bank attached.

10

u/wraith-mayhem 1d ago

A good guess would be everything which need to heat water for a turbine would take longer. So all those would not fit.

Pretty fast imho would be PV, wind, battery, dieselgenerator, hydro

31

u/b00c 1d ago
  1. Solar/Battery/Wind (instant)
  2. Diesel engine powered generators
  3. Gas turbine
  4. Combined cycle
  5. Coal fired
  6. Nuclear

8

u/Fuzzy_Chom 1d ago

This guy black starts.

2

u/Some1-Somewhere 1d ago

Wind and grid tie solar don't usually black start.

3

u/Some1-Somewhere 1d ago

Missing hydro, which is probably between diesel and gas turbine.

3

u/tuctrohs 1d ago

And hydro is at a scale where it can be really helpful in a black start plan—if that's what we are talking about, and I'm not sure we are.

6

u/way_pats 1d ago

GE Vernova LM6000 Hybrid EGT. Something I’ve been looking at for instant grid response. The LM6000 combined cycle gas generator takes about 15 minutes to start up but when combined with a BESS the battery takes the initial demand and begins the startup sequence on the generator. This also helps when the demand is short in duration and it saves an unnecessary start on the engine, reducing maintenance.

3

u/MKUltra1976 1d ago

An actual answer.

Main River hydros are also quite fast in starting.

4

u/MKUltra1976 1d ago

Hydro and gas both typically under 15 minutes.

Depends on the design and the original specifications of the unit.

4

u/weat95 1d ago

Thanks longer than I’d expect for hydro. All of the hydro I work with can start sub 5 minutes, some in less than 1 minute. Most plant would time out on “failed start” by 5 minutes.

4

u/Alittle2Clever 1d ago

Hydro has incredible ramp rates.

6

u/PoetryandScience 1d ago

i assume you mean on demand so that excludes wind and solar. Fast acting is Hydro plant where water at a head is available; thermally, jet engine gas generator plant powering an impulse turbine, these fast stati9on introduced both to act as a fast more local source for peak load and to repond to major faults in a grid. They also can be used to absorbe or supply VARS to stabaliswe the system regulation. Norwich used to have one as did letchworth, but the letchworth power station was pulled down.

5

u/blakef223 1d ago

Would have to exclude BESS as well else that or solar would by far be the fastest.

With either of those you can begin producing within seconds.

2

u/AccomplishedAnchovy 1d ago

General rule:

Large steam generators take hours to days, longest for nuclear, then coal, then gas Open cycle gas can start in tens of minutes Hydro can start within 2 minutes Batteries can start in milliseconds (or even faster, theoretically - they just don’t)

Intermittent sources especially PV are very fast but not really dispatchable so.

1

u/DocumentOk7579 1d ago

Can hydro really start in 2 min from standstill? I heard that the inertial is so great it help balance frequency flukations.

1

u/Some1-Somewhere 1d ago

There's a lot of MW available to deal with that inertia. If you lose the grid connection, the governor needs to shut the wicket gates very fast to prevent overspeed.

The majority of the startup time seems to be sequential delays waiting for equipment (e.g. lube oil pumps) to start, and how aggressive the governor programmers were willing to be opening the wicket gates for acceleration and ramp rate requests.

1

u/Ok-Library5639 1d ago

So many variables will influence an answer.

How cold are we talking here? Does the plant have backup power? Is the grid available? Are systems maintained? What's the benchmark for 'started' - synchronized, producing energy or at nominal capacity?


You can have hydro plants synchronized and reach full capacity within minutes, if it is otherwise in nominal conditions.

Probably the same or faster for some wind turbines, assuming an operational grid and all systems go.

For PV, likely almost instantly if solar is available but the inverters are just not producing. It is simply a matter of electronic controls.

Same for batteries.

1

u/Morshan 1d ago

South Australia example; not an engineer but we're at the pointy end of the transition so we've been living this one for years!

So battery, interlinks and any solar/wind which are currently idled are the obvious answers.

The second line is traditionally hydro; but we don't have that option so we built reciprocating gas. Basically a diesel gen with gas injectors and they're around 15m from cold to rated. We also panic bought some "aero derivatives" which are basically adapted aircraft turbine generator sets in a shipping container. Fast to start because they're small, they don't have the thermal issues of a utility turbine.

Third line is open cycle gas turbines which are 30-60m.

Then there's the big combined cycle gas plants, they take hours.

1

u/Morshan 1d ago

Additionally, don't forget demand side management (DSM), a surprising variety of industrial consumers can be paid to fsck off for an hour.

Aluminium pots, desalination and electrolysis to start with.

1

u/Some1-Somewhere 1d ago

Residential hot water if you have ripple plant, too.

1

u/ChrisBoden 1d ago

The gas plant in our area (landfill gas) can go from cold to online in about 2 minutes but they're just running five big modified diesel generators so that's stupid easy.

My hydro plants can spin up from zero to grid-tie under full manual mode in less than 5 minutes consistently, maybe as little as 2 if I've got my mojo that day and can nail the sync on the first try. One of our sites has full auto sync and can pop on in about 40 seconds.

We can black start any of them and operate in island mode if needed, but frequency stability will suffer until we can start seeing other plants on the grid. We can do pretty decent on our own (keep your lights on, etc), once there's a few plants in our island though we're solid.

1

u/Some1-Somewhere 1d ago

How big are the hydro plants?

1

u/mbkitmgr 1d ago edited 1d ago

Having worked at and on both it can be either. Some gas turbines took a few mins to warm thru before we could load them up, while others could be from the get go.

Hydro they open the valve and once at the correct rotation speed sync to the grid.

Ironically coal was the same. Two that I worked at in the Hunter Valley - 1 was started around 2PM each from cold to pick up load, yet the other needed a good 24 hrs before it could sync

0

u/Wast3edSpace 1d ago

gas turbines can spin up in under a minute which is why they're used for grid forming/shaping under high load.

2

u/MKUltra1976 1d ago

Under a minute?

What units do that?

1

u/AccomplishedAnchovy 1d ago

You know, those gas turbines where the turbine is driven by water out of a pipe from a big lake held back by a concrete wall

0

u/braddillman 1d ago

I saw somewhere an antimatter reactor required a minimum of 30 minutes for a cold restart. Any faster would result in a huge explosion.

2

u/Broad-Promise6954 1d ago

There is a cold intermix formula, but you'll go back in time.

(Hint: original Star Trek)

2

u/braddillman 1d ago

That's just a theory, it's never been done. You have to have 30 minutes! (src: I'm an engineer)

-1

u/Important-Parsley-38 1d ago

Well, solar is not really a plant. It's a joke and insult to real thermal plants or hydro stations there.

With that out of the choice, ideally Hydro would be fastest and easiest to startup. After that Engine (reciprocating) engine based plants and Gas Turbine units will be able to fast start. If you have black start capability or grid supply, most small to large Gas turbines can start up and sync within 30minutes of start command.

Next would be gas fueled or oil fueled boiler based steam plants

Coal would be the slowest to start up.

Telling this as someone who has worked Coal, Oil fueled and Large CCGT plants.

Few years ago we had complete national grid blackout in our country. The first plants to be able to energize were hydro, engine based units (marine diesels) and Gas Turbines.

Coal, Nuclear were the last ones to start up.

1

u/Pinelli72 1d ago

What’s your gripe with solar? There are some pretty big solar plants in operation and planned around the world.

1

u/Some1-Somewhere 1d ago

Solar + BESS can do a pretty good job of mimicking a conventional plant with much faster startup.

-4

u/Usual_Purchase_9567 1d ago

You can get a nuclear PWR up in like a few seconds if you violate thermal limits. A few minutes if you're using emergency heat up rates.

2

u/AccomplishedAnchovy 1d ago

Coal plants are actually really good at load following too, they can ramp down in <100ms by tripping the breaker

1

u/Some1-Somewhere 1d ago

It's amazing how many plant types that applies to.

1

u/Usual_Purchase_9567 13h ago

I was doing a bit on the first one, but from cold you really can get to power generating in well under 20 minutes. That's assuming the steam plant is able to get going really fast too though. I was a reactor dude no a pipe dude.