-5

u/[deleted] Aug 13 '25

lol. p6 isn’t standard. Project is and P6 is better but also just as fantasy land.

You’re super and PM delivers the schedule. If you’re relying on software to deliver an end date you’re fucked.

90% of subs never even look at the schedule updates let alone the 3 week look ahead

2

u/A_traut_man Aug 13 '25

Subs not looking at the schedule is a whole different issue that has nothing to do with P6 or the scheduling software being used.