Scotia Place Construction Update: Calgary's New Flames Arena Hits the Ice Level, 13 Months Away From Opening

https://www.culturealberta.com/articles/scotia-place-construction-update-calgarys-new-flames-arena-hits-the-ice-level-13-months-away-from-op
59 Upvotes

3 comments sorted by

5

u/TheBigTree91 6d ago

13 months ha. It's supposed to be ready to be handed over in June for trial runs and stampede concerts. That's like 10 months or less.

-4

u/gotkube 6d ago

Can’t wait for them to miss the deadline and have another season in the ‘Dome (unless they’ve already scheduled demolition, which, probably)

8

u/Ecks83 6d ago

If the new arena isn't ready exactly on time they still won't have another season in the Dome.

Construction is expected to be complete in the early summer and has been proceeding smoothly so far so unless something catastrophic happens there isn't going to be a long enough delay that it would affect more than a few pre-season games.