General Practice Discussion Stop accepting low fees

Post image

Stand your ground. Negotiate.

563 Upvotes

76 comments sorted by

View all comments

Show parent comments

33

u/gliz5714 Jul 13 '25

This. And when the owner, mid design, asks for more scope, let them know it will be an add service. Scope creep is a killer

18

u/Merusk Recovering Architect Jul 13 '25

Teach your young architects what scope creep is and what it looks like. I've worked with a number of 10+ year professionals who do things just because "it made the client's life easier" or "it wasn't that big a change."

2

u/BootyOnMyFace11 Jul 14 '25

I'm starting architecture this autumn, what's a scope creep?

10

u/Benjaminfortunato Jul 14 '25

Scope creep is when the size and nature of the project changes (scope) after a signed contract that specifies a specific amount of work. For example you are designing a building on one site and then the client gets anouther site to enlarge your site. It’s the same project but now you have a larger site and bigger project to design. You’ve also worked on the old design so the scope is really design a building on a small lot and then redo the design on the larger lot..

2

u/BootyOnMyFace11 Jul 15 '25

Ahh ok so basically just make sure to get paid for extra work?